低压湿式气柜维护维修规程

来源:六九路网


低压湿式气柜维护检修规程

二○○七

目 录

1 总则 ··························································································· 61 2 3

完好标准 ····················································································· 61 低压湿式气柜的维护 ······································································ 62

3.1 维护 ···················································································· 62 4 5

3.2 常见故障及处理方法 ······························································· 63 低压湿式气柜的定期检查 ································································ 低压湿式气柜的修理 ······································································ 65

5.1 检修周期及内容 ····································································· 65

5.2 检修方法及质量标准 ······························································· 67

5.3 气柜的补漏 ··········································································· 70 5.4 防腐 ···················································································· 73 6 7

试车与验收 ·················································································· 75 维护检修安全注意事项 ··································································· 79

60

1 1.1

总则 适用范围

参照原化学工业部颁布的《低压湿式气柜维护检修规程》(HG25007-91)以及《金属

焊接结构湿式气柜施工及验收规范》(HJG212-83)等有关技术规范、资料编制本规程。

本规程适用于水煤气气柜和燃料气气柜(5000m3 螺旋导轨式低压湿式气柜,以下简称为“气柜”)的维护检修。 1.2

结构简述

低压湿式气柜是可变容积的储存气体的设备,一般用于储存城市煤气、化工生产中的原料气、半水煤气或水煤气及其它气体。在化工生产中除起着均衡系统负荷和缓冲作用外,同时也具有对工艺气体净化除尘的作用。

低压湿式气柜主要由水槽、中节、钟罩、外导架、导轨、进气室、出气室、进气立管、出气立管、最高(最低)限位装置、配重等部件构成。中节、钟罩依靠导轨、导轮在水槽中自由升降而改变储气容积。按升降形式可以分为螺旋导轨式、外导架直升式、无外导架直升式等三种。 2 2.1 2.1.1 2.1.2 2.1.3 2.1.4 2.2 2.2.1 2.2.2 2.2.3 2.2.4 2.3 2.3.1 2.3.1.1

1.

完好标准 零、部件

各零部件完整齐全,质量符合要求。

最高、最低限位联锁、讯号、自动放空装置等齐全, 灵敏,准确。 管道、管件、阀门、支架等安装合理、牢固、完整,涂色符合要求。 防腐、保温、防冻、避雷、防静电、照明等设施完整有效, 符合要求。 运行性能

各塔节升降正常,压力均衡,无脱轨、卡轨等现象。 导轮、导轨润滑良好,油杯齐全,油质符合要求。

无异常的震动,塔节间无摩擦,导轮座及导轮连接螺栓无松动。 储气量达到设计要求或查定能力。 技术资料

设备技术档案齐全、准确。应具有: 施工单位所提供的气柜交工文件,包括 钢材、配件和焊接材料的合格证书;

61

2. 3. 4. 5. 6. 7. 8. 2.3.1.2 2.3.1.3 2.3.1.4 2.3.1.5 2.3.1.6 2.3.1.7 2.3.1.8 2.1.3.9 2.3.2 2.4 2.4.1 2.4.2 2.4.3

主体结构的组装记录及排版图; 气柜底板严密性试验记录;

气柜焊缝的检查记录,水槽壁焊缝的无损探伤记录; 气柜总体试验记录; 气柜防腐记录; 基础沉陷观察记录; 设计变更文件。 安装使用说明书。 设备履历卡片。

设备总装配图、主要零部件图及易损件图样。 设备运行累计时间。

设备缺陷及历年事故情况记录。 设备检修、试验与技术鉴定记录。 设备评级记录。 设备润滑记录。

操作规程、维护检修规程齐全。 设备及环境

气柜周围整齐清洁,无杂草、杂物,道路畅通。 水槽壁、各塔节壁板、顶板无漏水漏气。

进气室、出气室的溢流水封溢流正常,无堵塞、漏气,抽水装置齐全,应用可靠;

排水阀、上水阀、放空阀等无泄漏。 3 3.1 3.1.1

低压湿式气柜的维护 维护

气柜在运行中,操作人员应严格执行操作规程和控制储存气体(水煤气、燃料气)

的工艺指标,保证安全装置和防雷、防静电装置完好;特别要注意气柜的升起高度不得超过允许极限,以防止气柜被顶翻或抽瘪。 3.1.2

操作人员应经过考核合格后持证上岗,要做到“四懂”“三会”(即懂结构、懂原

理、懂性能、懂用途;会使用、会维护保养、会排除故障)。 3.1.3

按照岗位操作法的要求,定时、定线、定点进行巡回检查,巡回检查每班不少于

62

两次,主要检查内容有: 3.1.3.1

气柜的水槽、环形水封是否保持正常液位和溢流,有无跑气、跑水现象,要经常

给环形水封加注补充水,冬季要防止结冰。 3.1.3.2

气柜的导轮与导轨的接触、转动情况是否正常,导轮、导轨、导轮座的紧固情况

是否正常;要定期加油润滑,一般每月一次。 3.1.3.3

保持进出口小室、地下室的清洁,无积水;每四小时检查一次进出口小室各阀门

的开关情况和地下室积水情况,并及时抽去积水;遇下暴雨时要注意防止雨水倒流进小室;每月一次检查进出口小室的溢流水封,严防进出口小室水封被封死,必要时清洗积垢。 3.1.4

在有六级以上大风或雷雨天气时,气柜容积应控制2500m3左右,以防止机械变

形或遭雷击着火;气柜升降速度不得大于0.6m/min。 3.1.5

若气柜长期停车,应用氮气进行置换,直到气柜内的气体中CO+H2 的含量小于

0.5%(体积比)为止。 3.1.6 3.1.7

消除跑、冒、滴、漏,并做好防冻保暖工作。

专业技术人员定期检查气柜的避雷设施和接地地线,测量接地电阻是否符合有关

技术要求。检测工作每年至少一次。 3.1.8 3.1.8.1 3.1.8.2 3.1.8.3 3.1.8.4 3.1.8.5 3.1.8.6 3.2

出现下列情况之一时,操作人员应采取措施紧急停车,并及时向有关部门报告。 水槽、环形水封被冲破,气柜急速下降; 气柜倾斜;

卡轨,气柜不升不降、压力波动大; 自动放空水封泄漏,致使大量漏气; 容积失控,限位联锁装置失效;

发生其他危及气柜安全运行的意外情况。 常见故障及处理方法

低压湿式气柜运行中常见故障及处理方法如下表。

故障现象 整体倾斜 故 障 原 因 1.储气量超过规定的储气容积高度 2..基础沉陷 3.卡轨或脱轨 处 理 方 法 1.检查修理限位装置,降到规定的操作指标 2.详细检查沉陷原因,并作复位处理 3.更换导轮,调整导轮伸缩长度 63

故障现象 环形水封跑气 故 障 原 因 1.水槽水位高度低于环形水封高度 2.环形水封漏水或缺水 3.超过规定的储气容积高度 4.卡轨致使内压超过设计压力冲破水封 5.中节下部腐蚀 1.水封槽漏水或缺水 2.水封钟罩烂穿 3.内压过大冲破水封 1.进、出口立管腐蚀漏水 2.立管与水槽底连接处的焊缝开裂漏水 3.立管与基础之间密封材料失效漏水 4.溢流水封堵塞 5.暴雨时大量雨水倒流地下室 1.最低限位联锁讯号失效 2.进口小室水封封死 3.卡轨钟罩不降 4.操作失误 处 理 方 法 1.水槽加水到正常液位并保持溢流 2.加大补充水量,或停车检查修理水封 3.降低高度 4.检查导轨导轮并进行处理,加足补充水 5.降低使用高度或修理中节 1.水封加水使溢流正常 2.停止运行,检查修理钟罩 3.处理卡轨等缺陷 1.清洗溢流水封,排除积水 1. 采取堵漏措施,停车全面检查修理 2. 采取堵漏措施 4.清理溢流水封保持正常溢流 5.检查清理排水沟防止雨水倒流 1.立即停车 2.检查溢流水封排除积水 3.检查卡轨原因并进行处理,恢复钟罩自由升降 4.按操作法规定要求纠正误操作 自动放空跑气 进出口小室被水封死,地下室大量进水 抽负压 4 低压湿式气柜的定期检查

低压湿式气柜的定期检查分为外部检查、内外部检查、全面检查和非定期检查等四类。

4.1 4.1.1 4.1.2 4.1.2.1 4.1.2.2 4.1.2.3 4.1.2.4 4.1.2.5 4.2 4.2.1 4.2.2 4.2.2.1 4.2.2.2

外部检查

气柜的外部检查在气柜正常运行中进行,每季度一次。 外部检查的内容为:

气柜表面防腐层有无脱落,本体有无锈蚀,对于腐蚀部位应进行测厚; 气柜的焊缝等处有无裂纹、变形和泄漏等现象; 气柜的导轮与导轨吻合及磨损情况,导轮的润滑情况等; 气柜的基础有无下沉、倾斜或裂缝等现象;

进出口小室的溢流水封运行是否正常,必要时清洗积垢。 内外部检查

气柜的内部检查,应结合气柜停车或系统停车时进行,每年一次。 内外部检查的内容为: 外部检查的全部项目;

检查气柜内表面防腐层有无脱落,本体有无锈蚀;对于腐蚀部位应进行测厚以查

明腐蚀深度和分布情况。 4.3

64

全面检查

4.3.1 4.3.2 4.3.2.1 4.3.2.2

气柜的全面检查应结合系统停车大修时进行,一般每三年进行一次。 全面检查的内容为: 内外部检查的全部项目;

对各部位的壁板,尤其是腐蚀严重的部位进行无损测厚,如无条件进行无损测厚

时,也可钻孔(¢5mm)测厚, 然后补焊; 4.3.2.3 4.3.2.4 4.3.2.5

各环形水封及上体水封进行注水试验以检查泄漏情况; 进行气密试验;

进行升降试验;若气柜需进行补焊等检修工作,气密试验和升降试验则作为检修

后的检验工作,应在检修完毕后进行。 4.4 4.4.1

非定期检查

非定期检查就是提前进行气柜的内外部检查或全面检查,检查内容可根据实际情

况决定按内外部检查项目或者按全面检查项目进行。 4.4.2 4.4.2.1 4.4.2.2 4.4.2.3 4.4.2.4 5 5.1 5.1.1

在下列情况之一时,应进行非定期检查:

气柜在运行中或在气柜外部检查时发现有泄漏、变形,处于危险状态; 气柜停用一年以上,重新投入运行时;

气柜更换钟罩、中节或其它重要部件,或者进行局部补焊后; 根据气柜的技术状况,设备管理部门或使用单位认为有必要时。 低压湿式气柜的修理 检修周期及内容

气柜的检修分为定期计划检修和临时检修;定期计划检修根据检修间隔期和检修

工作量可分为小修、中修和大修;临时检修是由于某种原因而进行的临时检修。 5.1.2 5.1.2.1 5.1.2.2 5.1.2.3 5.1.3 5.1.3.1

1. 2.

检修周期如下:

小修,间隔期一般为一年; 中修,间隔期一般为三年; 大修,间隔期一般为六年。 检修内容 小修:

气柜的内部检查; 气柜的局部补漏;

65

3. 4. 5.1.3.2

1. 2. 3. 4.

气柜的导轨检查、清洗,添加或更换润滑油(脂);更换个别磨损严重的导轮; 气柜内、外表面的局部防腐。 中修:

包括小修的所有项目;

消除中节、钟罩壁、环形水封、顶棚板泄漏; 水槽壁及底板检查修理;

检查、调整导轮与导轨的接触间隙和磨损情况,对转不动的和磨损严重的导轮进

行修理或更换;

5. 6. 7. 8. 9.

检查外导轮和螺旋导轨的连接固定螺栓; 气柜外部检查、修理、防腐修补。

最高、最低限位安全联锁装置修理或调试; 进气室、出气室的排水泵检查修理;

进气室、出气室内部检查, 防腐修补,溢流水封清理、检查修理或更换;

10. 自动放空各部件检查修理或更换; 11. 所有阀门、管道检查修理或更换; 12. 照明、防雷、防静电装置检查调试; 13. 地下室混凝土构件检查处理。 5.1.3.3

1. 2. 3. 4.

大修:

包括中修的全部项目;

水槽检查修理,工字钢托座检查修理或更换; 导轨、立柱、构件检查测量,视情况修理或更换;

中节上下水封槽、钟罩下水封槽检查测量,视情况整形、修理或局部更换;中节、

钟罩环形水封蒸汽加热管检查或更换;

5. 6. 7. 8. 9.

中节、钟罩环形蒸汽加热管检查或更换;

中节、钟罩壁板、顶棚板、骨架检查修理,视情况局部更换; 进气室、出气室、进气立管、出气立管检查修补或更换; 气柜下沉量、倾斜情况检查测量校正;基础修补;

自动放空的水封、钟罩、放空管、手动放空阀检查修理或更换;

10. 配重块检查修理或更换,调整配重;

66

11. 内外壁全面防腐;

12. 上水管、放水管和蒸汽管的保温修补。 5.1.4

临时检修

一般情况下为气柜发生局部泄漏时进行补漏。 5.2 5.2.1 5.2.1.1

检修方法及质量标准 检修前的准备工作

确定检修内容,制订检修方案,编制检修计划和检修进度。钟罩、中节和水槽等

主要构件有较大面积需更新时,其施工方法和质量标准要按《金属焊接结构湿式气柜施工及验收规范》(HGJ212─83)执行。 5.2.1.2

检修前对检修人员进行任务、技术、安全交底,检修人员应熟悉检修规程和质量

标准。对于气柜存在的重大缺陷应提出相应的技术措施。 5.2.1.3 工具。 5.2.1.4

气柜在进行内部检查、全面检查或进行检修前,必须按照化工部颁发的《化工企落实检修所需的材料与备件,校验检修中使用的量具、仪器,准备好检修所需的

业安全管理制度》和《化学工业部安全生产禁令》中的有关规定,做好设备、管路的切断、隔绝、置换、清洗等项工作,经分析合格后方可移交有关人员进行检查或检修工作。 5.2.1.5

1.

气柜气体置换时应采用惰性气体。

经检修的气柜投入使用前,用惰性气体(氮气)置换气柜内的空气,然后用储存气

体(或工业气体)置换,经分析合格后方可投入运行。

2.

运行中的气柜需检查或检修时,先用惰性气体将气柜中工业气体置换掉,经分析

合格后,再用空气置换惰性气体,其氧含量达到21%时(与大气中含氧量相同)方可进行施工。尤其应引起注意的是,若水槽中存满水时,虽然检修前气柜内已经置换合格,但水槽的水中已被水煤气所饱和,可燃气体和有毒气体从水中解析出来,仍有可能引起爆炸或中毒事故。因此必须采取相应的安全措施,如将水槽中的水排尽,加强气柜的通风等等。 5.2.1.6

1.

气柜达到下列条件后,生产部门方可移交检修部门检查或检修:

气体出入口管道的阀门关闭,并已加上盲板,使之与系统隔绝;将所有放空阀打

开,用氮气置换合格。

2. 3.

放水,打开水槽人孔,进行空气置换。 气柜内含氧量为21%,通风良好。

67

4. 5.2.2 5.2.2.1

经分析合格后,主管领导签字。 材料

气柜检修所用的型钢、钢板、钢管、焊接用材、油漆等要符合设计要求,并有出

厂合格证明书或材料复验证明书。 5.2.2.2 得使用。 5.2.3 5.2.3.1

预制件

立柱在下料前均应检查调实,预制好的立柱断面扭曲不大于2mm,纵向直线度全用于壁板和钟罩的顶棚板的钢板必须加以选择,锈蚀、麻点、凹陷严重的一律不

长不大于3mm。 5.2.3.2 5.2.3.3

螺旋导轨加工后其弯曲弧度偏差为:径向±5mm,侧向±3mm。

螺旋导轨、立柱自身对接采用V型坡口,对接焊缝的焊接工艺及选用的焊条必须

根据导轨、立柱的材质确定,焊缝凸起部分必须磨平。 5.2.3.4

螺旋导轨加工弧度符合设计要求,不得有过烧、裂纹、急弯、扭曲等缺陷,表面

锤击疤痕深度不得大于1.5mm。 5.2.3.5

导轨下部垫板对接焊缝应在导轨拼接前焊好,对接两弧之间不许有错边,焊接后

两面凸出部分必须磨平。 5.2.3.6 不涂漆。 5.2.4 5.2.4.1 补。 5.2.4.2

水槽底板不得有裂缝,发现时应把裂缝处清理干净,然后补焊,焊好后打磨平整,水槽、中节、钟罩

壁厚小于原设计2/3的部位,应进行更换;一般为挖补,面积小于0.5m2时允许贴钢板、型钢成型后要喷砂、除锈、防腐,涂底漆两道、面漆一道;焊缝处留出30mm

再贴补上一块钢板。 5.2.4.3

工字钢托座用光学水平仪找水平,相邻托座水平允差±2mm,直径方向对称托座

水平允差±5mm。 5.2.4.4

焊缝不得有裂纹、夹渣、气孔等焊接缺陷,咬边凹陷不得超过0.5mm,超过时应

在打磨后补焊。 5.2.4.5 5.2.4.6

钢板放样划线的样冲眼深不得超过0.5mm。

水封槽要以工字钢托座为基准找水平,整个圆周上的水平误差不得大于10mm;

68

钟罩或中节的水封槽,半径偏差在任何部位均不得超过设计尺寸的±20mm。 5.2.4.7

中节上水封的水平板在整个圆周上的平面度为10mm,水封立板其全高垂直允差:

倾向挂圈板侧不大于10mm,倾向上圈板侧不大于5mm,如图1。 5.2.4.8 5.2.4.9

上圈板和下圈板的直径允差如表1。 中节、钟罩的上圈板与下圈板组装垂

直度为2mm,水平偏差不大于5mm,直径差±10mm。 5.2.4.10 各塔节壁板垂直度为全高的1/1000,局部凹凸不大于30mm;壁板组装焊接时应注意被导轨垫板覆盖的焊缝的焊接,保证严密性;钟罩与中节之间的间隙与设计尺寸的误差不得大于±20mm。

5.2.4.11 下水封焊缝注水试漏检验应合格;其

它焊缝按JB2880《钢制焊接常压容器技术条件》的规定施工焊接。 5.2.5 5.2.5.1

导轨、导轮 表1. 更换螺旋导轨在安装前要复查壁板的上、

水槽壁直径 mm 10000~20000 20000~30000 > 30000 允许偏差值 mm < 10 < 15 < 20 下水封处的椭圆度, 其直径允许偏差为±15mm,被螺旋导轨及垫板所盖的壁。板焊缝必须在导轨及垫板安装前进行透油试验,确认无渗漏现象。 5.2.5.2

螺旋导轨更换安装前根据设计位置和螺旋升角在壁板(或立柱)上标出导轨螺旋

线的基线,第一根螺旋线应按设计要求校正基线位置和螺旋升角,并以此线为基准线校正圆周上其他各螺旋线的间距,其偏差应不大于5mm;然后沿螺旋线分上、中、下三点焊好定位角铁;导轨点焊后应分3~5点检查各相邻两导轨轨面中心周向距离, 相邻两导轨的平等度偏差为±6mm,与基准圆径向允许偏差为±5mm。 5.2.5.3 5.2.5.4 5.2.5.5

待所有导轨就位并校正位置,符合要求后方可焊接导轨和上、下圈板间的焊缝。 导轨检修完工后,焊瘤应铲平磨光。

导轮安装应当在钟罩、中节本体检修焊接工作全部结束后进行,导轮安装前必须

校验所有螺旋导轨与气柜的中心偏差,用铅垂线在每根导轨的上端、中间和下端三点进行测量,其径向、周向偏差都不应大于高度的1/1000,且不大于15mm。

69

5.2.5.6 导轮安装时导轮轮缘凹槽和导轨的接触面应有3~5mm的间隙,导轮的径向位置

要满足导轨升降时任何一点均能顺利地通过导轮,而导轮的轮槽中心线则应偏离切线方向3~5度,以利于导轨上升;导轮在不接触导轨时应能自由转动。 5.2.5.7 油杯。 5.2.6 5.2.6.1

拱顶骨架

拱顶骨架的主、次梁安装前必须检查预制件的长度和形状偏差,直梁的直线度为导轮轴与导轮孔之间为间隙配合H11/d11,轴与孔必须清洗,加足润滑油,装好

20mm,拱形梁的线轮廓度为20mm。 5.2.6.2

中心环位置及标高要符合设计要求,并作预先校正,然后安装主梁,应对称安装

成十字形,再对称安装其余梁,相对的主梁必须通过中心环的中心,并成一直线,其相对于环中心的偏移量不大于5mm。 5.2.6.3 5.2.7 5.2.7.1

拱顶骨架直径偏差±10mm,水平偏差不在于5mm,垂直度偏差10mm。 水槽内立管、配重块

水槽内立管的垂直度为全高的1/1000,钟罩顶盖上的切断套筒和立管有足够的间

隙,中心偏差不大于10mm。 5.2.7.2

配重块要逐个称重,按设计要求分组组合,重量相等的两组对称布置;布置配重

时应考虑到螺旋梯等不对称布置的构件重量的影响。 5.3 5.3.1 5.3.1.1

气柜的补漏

水槽、中节、钟罩顶棚的堵漏方法

带压攻丝堵漏,适用于泄漏面积小的裂缝、小漏孔,具体方法是在气柜本体上先

钻孔、攻丝,然后再加丝堵。 5.3.1.2

带压钩头螺栓堵漏, 适用于小裂缝、小洞孔,具体方法是在气柜上用90°的钩头螺

栓塞入裂缝或孔洞内钩牢内壁, 外复填料和钢板, 然后拧紧螺栓。 5.3.1.3

带压焊接贴补消除泄漏,适用于泄漏点多、面积大的情况,一般在停车后进行。

用鼓风机或压缩空气,把中节和钟罩逐渐升高,再进行贴补焊接。漏气量大的可以在贴补的钢板上开孔,焊上一只螺母作排气孔,然后贴补焊接。如周边漏气量大,可以用石棉线堵塞,阻止漏气。焊好后在螺母上拧上螺栓,再将它焊死,割除多余部分。 5.3.2 5.3.2.1

不停车补漏

低压湿式气柜的水槽、中节、钟罩顶棚发生局部小裂缝时,在必要的情况下采取

70

了适当的安全措施后,可以进行不停车补漏,但应尽量避免。不停车补漏的方法一般有两种:焊补和用粘接剂局部修补。 5.3.2.2

1. 2.

焊补

裂纹很小,没有发生水煤气泄漏或漏气量很小时可以直接焊补。

裂纹较宽,并且已发生水煤气泄漏时,可由佩带氧气呼吸器的人,用锋利的黄铜

凿子将石棉绳凿入裂缝内,并用腻子敛缝,消除水煤气泄漏后,再在外面补焊钢板。

3.

裂缝较宽,水煤气泄漏量很大,无法敛缝者,可带煤气焊补钢板。焊补时气柜中

水煤气压力应保持在20~30mm水柱范围内,压力太低易发生回火;压力过高,则将熔化的焊条吹出。 5.3.2.3

1.

粘接剂局部修补 环氧玻璃钢法

应用玻璃纤维增强环氧树脂,可以修补大面积的裂纹、裂缝和本体腐蚀。施工步骤为:表面处理,化学处理,底漆,填腻,涂贴环氧树脂和玻璃纤维布,涂面漆等工序。

⑴ ⑵

表面处理, 使用刮刀、钢丝刷等工具清除表面铁锈。

化学处理,使用二甲苯等溶剂脱脂,如果铁锈难于清除,则可用单宁酸涂刷,一

小时后刷底漆。单宁酸和铁锈生成稳定物质,使金属表面更符合涂料施工的要求,并延长涂层的寿命。

底漆,用环氧富锌漆作底漆,除了起一般涂料的保护金属作用外,当金属浸入水

中时,还能产生阴极保护作用。

填腻,用环氧树脂E44(6101)加上红丹粉或钛白粉调成浆状,配入聚酰胺树脂(650)

或β羟乙基乙二胺,填满表面不平的腐蚀坑或漏洞,以减少粘贴玻璃纤维布时可能出现的气孔和气泡。

贴玻璃纤维布,在填腻子的部位,涂刷E44(6101)树脂,然后贴玻璃纤维布(厚

0.1mm,宽150mm),布与布间搭接15~20mm,共贴三层,各层布的纤维方向应互相交错。

涂面漆,涂贴表面经过24小时固化后(六小时内不能淋水),再用环氧树脂、铝粉、

聚酰胺面漆三度罩面。

2. ⑴

粘接法,施工方法如下:

除锈,用手锤、刮刀、锉刀、砂纸等各种工具,将气柜壁泄漏处周围表面的铁锈

层除掉,露出金属光泽,再用洒精等溶剂脱脂。

71

⑵ ① ②

堵漏

如果泄漏处漏气,可先用泡沫塑料或棉花将漏处堵住。

用88#橡胶水(沈阳市橡胶厂产品)贴胶皮。用木锉打毛自行车内胎或废球胆等薄

胶皮,分别在胶皮和泄漏处周围刷上一层88#橡胶水稍干后,再刷第二层,然后等两者胶水都基本干时,迅速将胶皮贴在泄漏处,用力压实,从漏处向四周赶实,达到堵漏目的。

粘贴,在胶皮外面用环氧914或氯丁橡胶浆粘贴白布,以增加胶皮的强度;粘贴

程序与用88#橡胶水粘贴胶皮相同。之后,再涂刷氯磺化聚乙烯涂料5~7遍, 每遍间隔半小时, 作为防老化保护层。

氯丁橡胶浆的配方如下(体积份数):

粘接型氯丁橡胶 100 MgO(混炼后压成胶片)

4

FeO(溶于甲苯中) 4 PbO 5 防老剂D 2

将上述配方混炼后压成胶片溶于甲苯中,胶料与溶剂为1∶3, 配成胶浆。 硫化剂:聚异氰酸(JQ-4或JQ-1)。

胶浆与硫化剂为100∶15~30(重量比),现配现用。 ②

氯磺化聚乙烯涂料,该产品为A、B两组分,A为胶液,B为硫化剂,其配比为A∶

B=2.3∶1(重量比),现配现用。

3. 堵漏胶。

J型快速堵漏胶可以堵漏,也可以与M型胶HD-20J型堵漏胶配合使用。此胶适用于氯气、煤气、氧气、二氧化碳、二氧化硫、氨气、硫化氢、石油液化气氟气等介质的快速堵漏。

G型快速堵漏胶是单组分因态胶,可以使用,也可以与M型-20F型堵漏胶配合使用,应用于自来水、冷却水等水类介质的快速堵漏。

4.

在进行粘接剂局部修补的施工中要注意安全,采取必要的措施预防水煤气CO中胶补法快速堵漏,适用于小面积的洞孔、裂纹和裂缝。常用的有J型和G型快速

毒或修补中所用各种化学试剂中毒,要防止水煤气着火等事故发生。 5.4 5.4.1

72

防腐

低压湿式气柜在运行中,由于水煤气、水、大气等介质对壁板的腐蚀作用,往往

导致壁板破裂或穿孔泄漏,大大缩短了气柜的使用寿命(据有关资料介绍,半水煤气气柜寿命为5~10年,城市煤气气柜寿命为15年)。气柜腐蚀最严重的部位在钟罩、水封壁板干湿交替的水线附近、水封下杯圈及水槽底部。腐蚀的原因是电化学腐蚀,主要包括水煤气的腐蚀、水的腐蚀、硫化氢的应力腐蚀破裂、大气腐蚀和细菌腐蚀等。水煤气中的H2S、CO2、O2、有机硫等组分都具有腐蚀性,它们的水溶液也是一种强电介质溶液,在与水煤气接触的气柜壁表面覆盖了一层薄薄的液膜,产生“H2S-CO2-O2-H2O”的“液膜态”电化学腐蚀。其中H2S是主要的腐蚀成分,CO2 和O2起着加速腐蚀的作用。在H2S对碳钢的腐蚀中,“液膜态”的腐蚀速度远高于气相中的H2S的腐蚀速度,也高于液相中H2S的腐蚀速度。据有关资料介绍,在半水煤气中进行挂片试验时,碳钢在液相中的年腐蚀率为0.041mm,在气—液相中的年腐蚀率为0.144mm,在实际生产中局部位置的年腐蚀率可以达到0.50mm左右。同时在缺氧的条件下,细菌对硫化物、有机硫发生还原作用,产生H2S,从而加速对气柜的腐蚀。“液膜态”腐蚀的主要特征是均匀的斑点腐蚀。 5.4.2 5.4.2.1

低压湿式气柜在运行中, 可采取下列措施以防止或减缓气柜的腐蚀。 改变腐蚀环境

水煤气应进行除尘、脱硫等净化处理,严格控制硫化氢的含量在规定的范围内。要定期更换或连续补充水槽中的水,经常让钟罩、中节水封在水中起落,以便使水封得到冲洗,水封水得到更换。若由于水槽中水量很大,水中一般含有氰化物、硫化物等有毒物质而不允许排放时,应在水槽中加入缓蚀剂以减少腐蚀。 5.4.2.2

合理设计和施工

在制作新的钟罩、中节或修理中,尽量采用对接,避免搭接并采用合理结构;在焊接施工中,下料必须准确,采用合理的装配和焊接工艺,避免强制装配,焊后应锤击焊缝以降低或消除残余应力;采用的钢板在使用前应进行无损探伤,钢板不得有裂缝、夹层等缺陷;要选用较长、较宽的钢板,以减少焊缝,减少早期应力腐蚀破裂,并考虑适当增加钢板厚度。 5.4.2.3

涂刷防腐层

在低压湿式气柜的金属表面涂刷防腐层隔绝腐蚀介质,是气柜防腐的主要手段,必须高度重视涂料的选择、配套、施工质量和日常维护。

1.

气柜的所有金属构件,在焊接完毕并经检查合格后,进行防腐工作。

73

2. 油漆防腐前应将金属表面的污物、铁锈清除干净,宜采用喷砂处理或风动钢丝刷

除锈;预制件油漆时,安装焊缝处应留出不刷。

3.

水槽底板表面的防腐工作应

在底板严密性试验合格后进行。水槽底的防腐设计如图2。下水封的内外表面油漆应在注水试验合格后进行;进气管的内外表面油漆应在安装前进行,如需脱脂亦应在安装前进行。

水槽、中节、钟罩内表面及气柜内的管道、结构等油漆应在水槽注水试验前进行完毕。但水槽、中节、钟罩的外表面在安装期间只刷底漆并留出焊缝

不刷,待严密性试验合格后补刷油漆焊缝并最后完成防腐工作。

4.

气柜各构件中互相重叠的表面防腐工作应配合施工工序及时进行,以免事后无法

涂刷油漆而影响质量。

水煤气气柜的配套涂层如表2。 表2.

方案 内 壁 外 壁 水 槽 底 备注 1.水槽底涂层配套设计详见图2 2.被涂面必须喷砂处理 3.天津油漆厂供货 被涂面必须喷砂处理 本方案各种油漆均由上海开林造漆厂供货 推荐在1000m3以下的煤气气柜上使用 一 底漆, 云铁环氧底漆一道 面漆, H41-4环氧沥青漆3~4遍 二 底漆, H06-环氧富锌底漆一道 中间层,HL-901环氧沥青管道漆或846-1环氧沥青漆一道 面漆,HL-902环氧沥青管道漆或环氧沥青漆一道 底漆, L44-81铝粉沥青漆1~2道面漆, L44-82沥青漆3~4道 三 底漆同左 底漆同左 中间层H41-4环氧沥面漆H53-34环青漆3~4道 氧沥青漆1~2道 面漆, 651铝粉,氯化橡面层 发热沥青胶防锈漆或云铁氯化橡漆一层8mm 胶桥梁面漆1~2道 底漆同左 中间层624云铁氯化橡底漆同左 胶防锈漆二道面漆 651铝粉氯化橡胶面漆 或云铁氯化橡胶桥梁面面漆同方案1 漆二道 底漆同左 中间层同左的面漆 底漆同左 面漆同方案一或二的面面漆同方案1 漆 74

方案 内 壁 磷化底漆Y06-1一道,过气乙烯底漆G06-4一道 过渡层 G06-4:G52-1=1:1一道,过氯乙烯防腐漆二道 过渡层 G52-1:G52-2= 1:1一道,过氯乙烯防腐清漆G52-2四道 外 壁 水 槽 底 备注 四 同左 最后涂1~2道铝色过氯乙烯防腐漆 同上 5.4.2.4 1.

对水煤气气柜防护涂层的维护应注意以下几点: 涂层施工后最好不再施焊。若涂层因焊接烧坏或机械碰坏,则必须进行内外修补。

修补前, 还必须清除损坏的涂层,然后按涂层配套方案逐层涂刷。

2.

要定期检查。涂层在使用过程中如有损坏或老化失效现象,要及时修补,以防止

发生严重的局部腐蚀。当大面积失效时,应将旧涂层全部清除干净后方能涂刷新涂层。如果旧涂层基本完好,则可保留结合牢固的旧涂层,涂刷与旧涂层相配套的新的有效涂层,如在沥青漆或环氧树脂上可涂刷环氧沥青漆等。

3.

对于使用不久的外壁涂层, 若原来未涂刷防老化面漆, 最好补涂1~2道相配套的

抗紫外线、耐干湿交替能力强的面漆,如上表中几种氯化橡胶面漆。 6 6.1

试车与验收 试车内容

低压湿式气柜在大修或中修完成后,应进行试车。试车内容如下: 6.1.1 6.1.2 6.1.3 6.1.4 6.1.5 6.2 6.2.1 6.2.1.1 6.2.1.2 6.2.1.3 6.2.1.4 6.2.1.5

水槽注水后,检查壁板有无漏水现象。

进行气气密性试验, 钟罩内气体压力达到工作压力时,检查焊缝有无漏气现象。 检查钟罩上升情况,有无卡涩现象。 检查和调整导轮与导轨的间隙。 测量气柜漏气量(根据实际需要确定)。 试车前的准备工作 试验前应具备以下条件:

检修项目全部完成,并有检修记录和有关的验收合格证。 所有管道都已安装好,法兰、盲板等处无泄漏现象。

钟罩底环和垫铁部分凡有点焊处全部割开,导轮转动灵活,一切卡具全部拆除。 防腐完工并检验合格,达到规定的养护期。 拆除脚手架,气柜内部清扫干净,封闭全部人孔。

75

6.2.1.6 6.2.1.7 6.2.1.8 6.2.2 6.2.2.1 6.2.2.2 6.3 6.3.1

装好测压用的水柱压力计。

安装好供升降用的鼓风机或准备好气源。 打开钟罩人孔,以防水槽加水时气柜上升。 人员组织

中修后试车由使用单位负责组织有关人员参加试车与验收。 大修后试车由主管部门负责组织有关人员参加试车与验收。 水槽注水试验

气柜的水槽进行注水试验时,应设专人及时检查水槽壁。若发现水槽壁漏水应立

即停止注水, 并做好记号, 将水位降至缺陷以下后进行补焊。补焊后继续注水试验直至合格。 6.3.2

在注水期间应对基础进行沉陷观察,如发现有沉陷现象应继续观察直至沉陷停止

为止。有异常沉陷必须立即停止注水,并采取消除、防止沉陷的有关措施。 6.3.3 6.3.4 6.4 6.4.1

水槽注水试验时间不少于24小时。 水槽注水完毕,封闭钟罩上的人孔。 气密性试验

在进行气密试验前,应在钟罩盖的中心人孔上安装临时的U形玻璃管压力计和温

度计(量程100℃, 长500mm)各一个。 6.4.2 力。 6.4.3

水槽注水试验合格后,开始向气柜内充气。随时检查气柜进出口管、放空管等各低压湿式气柜的进气管上接上压缩空气,压缩空气的压力应大于气柜额定操作压

处有关切断装置的严密性。 6.4.4

气柜充气后应经常注意压力计的指示数及各塔节上升的状况。如果在钟罩或中节

上升过程中压力突然升高,必须立即停止充气并检查有无阻碍上升的障碍物,消除障碍后才能继续试验。 6.4.5

当钟罩下水封立板靠近中节上水封挂圈板时应减速上升,并检查下水封内有无妨

碍扣合的杂物。此时必须沿圆周分几处同时观察下水封是否按正确地进入中节上水封,检查水封是否能挂合严密。 6.4.6

在钟罩和中节上升过程中,用肥皂水检查壁板焊缝,如有泄漏应随时停止试验,

待补焊后继续试验。

76

6.4.7 在钟罩和中节按设计要求升起后, 压力计指示数应与气柜设计压力相近, 此时用

肥皂水涂抹钟罩顶盖焊缝进行气密性检查, 如有漏气则应补焊。 6.4.8

顶盖部分气密性检查合格后,即可将顶盖中间的阀门打开或将一个人孔盖松开,

使钟罩与中节缓慢下降。 6.4.9

气柜接设计要求全部升足后,如压力计指示压力和设计压力偏差太大,则应重新

调整配重。 6.4.10

采用补焊法消除泄漏的,待气密性试验和升降试验完成后,必须打开放空阀及钟

罩顶部人孔,把水放干,开启各塔节人孔,搭设脚手架进行防腐修补。 6.5 6.5.1

升降试验

气柜的气密性试验合格后,应进行升降试验:即先作一次慢速升降,然后再进行

1~2次快速升降试验。快速升降试验中,气柜的升降速度每分钟不超过1.5m。如无适当设备供气而无法实现快速上升时,可只作快速下降试验。 6.5.2

在气密性试验合格后停止供气,打开放空阀,使中节和钟罩缓慢下降。在上升或

下降过程中应沿周观察导轮与导轨的接触情况,并做好记录,凡是导轮与导轨配合不好的,在二次升降前均应调整好,各导轮必须转动灵活,导轮与导轨之间的间隙在全行程中均不得大于15mm。 6.5.3

为进一步检查升降情况,在钟罩顶板预先开好测压孔(沿顶板外周长设6~8处),

安放U形压力计。并安排观测人员在各节升降过程中记录压力计所指示的压力变化。要记录每一个中节和钟罩升起后或下降后的工作压力,同时也要密切观察各节在升降过程中压力是否发生突然变化。如果压力有突然上升现象,则说明导轮与导轨之间摩擦阻力过大或者有卡碰之处。此时要立即停止鼓风,检查并调整导轮导轨,然后继续试验。每一节升起或下降后的工作压力,测定的结果应与设计的工作压力基本一致。 6.5.4 6.5.5 6.6 6.6.1

按设计要求全部升足高度后,实测压力与设计压力偏差较大时,要重新调配配重。 在气密性试验和升降试验中要调试安全联锁。 测量漏气

将空气压入气柜至气柜的有效容积的90%为止;放置24小时后再测量气柜的实际

容积,试验开始与终了时的容积差即为漏气量。 6.6.2

用下列公式将量度容积换算成标准状态下的容积:

3

V0=Vt m

77

式中:V0 干燥空气在0℃、压力为101325Pa时的标准体积,m3; V t 被测量空气在温度t、大气压为B及压力为P时的体积,m3; PS 蒸汽分压力,Pa; B 外部的大气压力,Pa; P 气柜内的空气平均压力,Pa; t 气柜内的空气平均温度,℃。

注:⑴气柜内的空气平均温度t 是在钟罩顶盖的不同位置上所测得的温度的平均数值,测量点应不少于3点;

⑵在试验开始及终了,如果温差相差不大,则蒸汽分压PS亦相差不大, 可以不考

虑;这时可按下式计算:

V0=Vt m 3 。

将试验所得的空气泄漏量乘以系数K换算为储存气体的泄漏量,气体的漏气量不

6.6.3

超过2%,则气柜的严密度为合格;否则要继续检查并消除泄漏部位。系数K按下式计算:

K= 式中:γ1 空气的比重; γ2 储存气体的比重。 6.7 6.7.1

验收

气柜经过水槽注水、钟罩和中节气密试验以及快速升降试验后,符合下列要求即

可认为试验合格,并可移交生产部门使用。 6.7.1.1 6.7.1.2 形现象。 6.7.1.3 6.7.1.4 6.7.2 6.7.2.1 6.7.2.2 6.7.2.3 6.7.2.4

78

所有焊缝和密封接口处均无泄漏。

导轮和导轨在升降过程中无卡涩、脱轨及因升降机构安装不当造成的壁板严重变

气柜各部位无严重变形。 安全限位装置动作准确。

气柜试验合格后, 负责施工单位应向使用单位提供下列竣工文件资料: 钢材、配件等合格证。

主体结构的检修记录和竣工图样。 焊缝泄漏检查、返修记录。 气柜总体检查封闭记录。

6.7.2.5 6.7.2.6 6.7.2.7 6.3 7 7.1 7.1.1 7.1.2 器具。 7.1.3 7.1.4

气柜总体试验记录。 基础沉陷观察记录。 防腐竣工验收资料。

填写竣工证明书,办理验收手续。 维护检修的安全注意事项 维护安全注意事项

严格控制气柜运行工艺指标,不准超高和超低运行。

维护检查时必须有两人或两人以上才允许进入地下室或登上气柜,并随身带防毒

开停气柜时,要确认钟罩放空活门与钟罩连通活门的位置是否正确。

气柜厂房应配备消防设施,并能正确维护使用,严禁明火照明、取暖以及将其他

火种带入气柜区域内。 7.2 7.2.1

检修安全注意事项

进入地下室维护检修时除办理设备交出检修证明书外,还要办理进塔入罐证明

书,并有两人或两人以上工作。如需动火应办动火证。 7.2.2 7.2.3 腐。 7.2.4

气柜停车检修时按规定的开停车方案进行,待置换合格后先开顶部人孔,保持通上气柜中节、钟罩维护检修时,应有两人或两人以上工作,并带防毒面具。 气柜隔离大修时盲板厚度不得小于10mm,且不得有裂纹、砂眼,并进行涂漆防

风良好,然后水槽放水;并严禁开启水槽壁人孔放水。 7.2.5 7.2.6

在检修前要检查有关安全器具,检修机具以及检修用电是否符合规定要求。 进入气柜、动火、临时照明、登高作业、立体作业、现场抽加盲板等操作要严格

执行《化工安全管理制度》和原化学工业部颁发的《化学工业部安全生产禁令》。 7.2.7 7.3 7.3.1 7.3.2 7.3.3 7.3.4

严禁检修、防腐同时进行。 试车安全注意事项

气柜封闭前应认真检查,并做好封闭记录。

水槽注水时必须打开钟罩顶部放空阀以防气柜注水时钟罩浮动。 注水速度要适当,不宜过大,以防水压波动影响系统生产。 各溢流水封在试车前应加好水。

79

7.3.5

在试车中要观察最低、最高安全限位联锁装置的动作和讯号是否灵敏准确。

80

因篇幅问题不能全部显示,请点此查看更多更全内容